Hi all, Things are really moving now! Every day there is something exciting happening. Saturday, Jan 4
The Northlake crew dug an extension to the footing for the wall between the driveways and poured it with some excess concrete from a pour across the street. Monday, Jan 6
Ralph was there doing the final crack repair and touch up from a list I had given him. He expects to finish in about an hour. Steve and I discussed ceiling heights, door clearances, areas for windows, etc. I have an appointment to talk to the framers at noon today. He has a crew of framers he uses when he is busy, or for large jobs. Both situations are true for our job. I talked to Scotty, one of the framers, and we went over all the ins and outs of the job. I gave him sketches showing all the doors and windows. The drawings done by a designer were adequate for the city permits, but did not show a lot of the details I want. In fact, I never had a chance to review the drawings until after all the permits were obtained. Scotty says they should be able to start our job on Thursday - Friday at the latest. After getting home and starting to work on a layout of the driveway wall, I got a return call from the garage door supplier who suggested meeting at the house in a half hour. As I had been trying to contact him for several days, I agreed. We discussed panel size, ceiling clearances, framing dimensions, and windows. After about a half hour we had decided on the door color, panel pattern, and window design. As the RV garage door is an odd size, 13 feet wide by 14 feet high, it is a factory order, so both doors are being ordered from the factory. They should be ready in about 2 weeks. Steve asked if I could do a CAD layout of the block arrangement, so it could be built to the correct contour prior to grading the actual driveways. I went back home and finished the layout. Tuesday, Jan 7
This afternoon, Steve was doing grading on the east side and front of the house. He then dug down to the electrical conduit he needs to extend to the house and then dug a trench from there to the house. He will continue to dig for the water and gas lines, with the phone and cable in there somewhere. When I left you could see the electrical conduit and the trench was dug all the way to the house. When these utilities are all buried, Fermi can finish the wall. Also, once the utilities are in, Steve can cut down the west side of the lot alongside the RV driveway. I am keeping the ground level even with the driveway all the way to the RV garage. It will then slope up gradually along the length of the garage to full grade height in the rear. I am now laying out the electrical outlets, lights, and switches for the garages and shop. If the framing is finished in about 2 weeks as Scotty said, the electricians will be right behind. Wednesday, Jan 8
Thursday, Jan 9, and Friday Jan 10
Friday afternoon, Betty and I drove to the north end of Phoenix and had dinner at Black Angus to celebrate anniversary #43. Saturday, Jan. 11
Steve dug a trench along the west side of the RV driveway for the water line to the RV garage. The line from the meter went to a shutoff valve just behind the meter (This is in addition to the one in the meter housing.) From there it runs to the pressure regulator and then to a tee. One side of the tee feeds the house, the other has another shutoff valve and feeds the RV garage hose bibs. The regulator, tee, and RV shutoff valve are at the bottom of a cement water meter housing. The shutoff valve just after the meter is in a large PVC pipe which extends up to the surface. Sunday, Jan. 12
Monday, Jan. 13
They start by matching "green board" to the footings and drilling holes for all the J-bolts and any conduits coming from the floor. They then mark the stud locations on both this board and the top plate. Studs are cut to the right length and the wall is nailed together. Of course windows and doors make the process slightly more complex, but the first walls had none. Before I left in the early afternoon, the rear car garage wall and the two short walls on each side of the door were all up and braced to be plumb and true. The 4 x 12 laminated beam header was lifted up to the top of the garage door and nailed in. They were in the process of fitting the last of the green boards around the RV garage and cutting a number of studs to build these walls as I left. Tuesday, Jan. 14
These wall sections of 2 x 6 studs a little over 12 feet high and about 16 feet long, some with window headers, are heavy! When all the sections were up, tied to each other and braced, Scotty was very anxious to get some "shear panels" in place to make them very stable. The entire RV garage is "sheared" using 1/2 inch OSB (chipboard). Once this is in place, there is virtually no movement of the wall along its length. I mentioned that the walls were a little over 12 feet high. These walls are built on a block wall that is about 42 inches high. The total floor to ceiling height of the RV garage is going to be 16 feet, 1 inch in the front, a little less in the rear as the floor slopes slightly toward the front for drainage. Wednesday, Jan 15
Steve was hoping the building inspector would arrive to buy off the front deck footing rebars, as he was hoping to pour the footing shortly when a concrete delivery for the driveway across the street came. The truck arrived and they partially poured the driveway when the inspector arrived. They were then able to pour my footings when they finished the driveway. Whew! After emptying the truck and filling all but about 5 feet of the footing trench they started leveling and troweling the footings. They try to set all the parts of the footing level, stepping it in 4 inch increments as the level changes. This allows the block wall to be built and end up level across the full length of the top. Steve had to run to the office, so I took over the transit duties. The workers would hold a tape measure just at the surface of the concrete, I would take a reading and tell them "Up 1/4", or "Down 1/8". They usually understood and did the correct change. Getting the footing accurate within 1/4 inch is close enough, as there is that much latitude in mortar thickness for the block layer. Betty and I drove out to the house near the end of the day. They had all the rafters in place up to the 45 degree gully where the patio roof meets the shop roof. I am not sure yet if I will have the ceiling just continue at the single slope all the way to the garage end of the shop, or if I should have the compound angle ceiling. I'll decide that tomorrow! Tomorrow morning they are having a crane (some are calling it a boom truck) come to lift the trusses up to the 16 foot level for the RV garage. I am sure they will also use it to lift the 4 x 12 laminated header to the top of the door opening of the RV garage. That should all be fun to watch. The next couple of days should have the garages, porches, and shop all looking pretty much like the finished items (shape wise). Then quite a bit of time will be spent putting on the finish siding, trim, roofing, deck, etc. I believe the electricians can come in once the interior carpentry is finished. I have been delaying the sending of this report until I had some significant progress to show. I will send it now and leave the more finishing stuff (like the roofs) until next time. I have posted some more photos on-line at: http://members.isp01.net/rmason/statusreports.html (that's this site) Till next time, Dick |
|
||||||||||||||||||||||||||
|
|