Hi all, Thursday, March 6
I was concerned when the first truck ran out of concrete with the job
well less than 1/2 poured. Then I found they had ordered 3 trucks.
Two came fairly early-on. They had to call to give the quantity of
concrete for the third. They ended up with just the right amount
of concrete to finish the RV driveway and two small concrete pads for the
front and rear landings from our front deck. They were there until
fairly late in the afternoon power troweling, hand troweling, edging, seaming,
and finally brooming it. It really looks good!
I noticed that the gas line had been re-connected and that the system
had been pressurized to 30 psi. I climbed the ladder and the pressure
was still at 30. (Later in the day, it was up to about 32 due to
the increase in temperature.) We can now order the gas meter to be
installed.
I completed installing all the outlets and switches in my shop, and
all but 5 in the RV garage. I then crawled under the house and fed
the phone and cable TV input wires through one of the conduits up to my
patch panel. I still am hoping to have the utilities install their
boxes on the garage wall under my patch panel. I then fed all my
TV, computer network, and phone cables up through the other two.
I am now just about ready to start installing the patch panel.
Tom and Scott along with a couple helpers went around the new skirting
cutting holes for air vents, and installed the trim strips. The painters
are coming on Saturday to do the outside painting.
Around 3:30 or 4:00, Ernesto arrived with a wheelbarrow of wet stucco.
He started putting the 2nd coat on the lower walls of the RV garage.
The carpeting is set to be installed on Monday.
Friday, March 7
I went to work installing the final outlets in the RV garage, as well
as installing nylon plates on my shop outlets and blank plates over all
the garage door control boxes and the mud rings I installed for phone,
TV, and data cables run through the conduits I installed. I had to
hurry along one wall, as I was not that far ahead of Ernesto and his stucco.
After finishing the outlets, I powered up the shop sub-panel by connecting
the heavy cable feeding it to a 100 amp breaker in the main panel.
I brought up one circuit at a time and checked out all lights, outlets,
GFCI's, etc. It all worked the first time! Even the 3 way and
4 way switch circuits. What a relief!
With the electrical finished (except, of course, the outside lights
which will be installed after painting is complete), I turned my efforts
to the patch panel. I cut a 3/4 plywood panel to 24 x 42 and mounted
it to the wall between the house electrical panel and the water heater
door. This is where I located the conduits to under the house and
the overhead ones to the shop and RV garage. I mounted the telephone
punch-down blocks and the network patch panel. I mounted this on
a hinge which I had to cut out (Oh for my mill!) and a couple of wooden
blocks. This mounts it along the board, but allows it to hinge out
for easy wiring access to the rear.
Tomorrow I will start wiring the phone and network cables.
Steve prepared the extended back patio and the pad outside the RV garage
rear doors for concrete, and nearly completed the outside grading.
Tom and Scott built the steps to the front of the deck and started the
ones at the rear of the deck.
The painters are supposed to come in the morning to prep and start painting
the outside.
Saturday, March 8
I concentrated on my patch panel today. I terminated all the phone
lines to the punch-down panels, then started on the network wiring.
I tried several methods of routing the wires so they would not be disturbed
too much when I swing the panel open to access the back. The hinge
I so laboriously cut out will not work. It stresses the wires too
much. I decided to replace the hinge and mount it differently.
An unmodified hinge, except for 1 added hole, mounted on the side of a
solid block of wood worked fine. I then punched down all the network
cables. Next I put connectors on about half the TV cables.
I decided that as long as I kept the locks Steve has a key for on the
garage door to the house and the garage door to the shop, i could replace
all the other locks with the new ones. They don't have keys for those
locks anyway. I replaced the front door locks, and the deadbolt locks
on Betty's and the garage doors. Now all the locks except the two
for the contractor use the same key. I can get rid of 4 keys from
my key ring!
I wrapped things up and headed for home. On the way home my cell
phone rang; it was Betty asking what my plans were. It was then I
realized that we needed to leave for church in about 30 minutes!
We have been attending the Saturday evening service. We made it just
fine.
Sunday, March 9
I finished putting connectors on rest of the TV lines. I think
I have gone as far on my patch panel as I can for now.
I had bought two 4 x 4 panels of 1/4 inch hardboard (yeah, I know -
"Masonite"!) I cut 4 pieces the right size for the attic crawl holes
(I am adding another in the garage) and a couple of pieces to make
covers for the two access areas for my conduit "junction areas".
Betty and I then went to Home Depot to finalize our selection of outdoor
light fixtures, and to get a first cut at choosing ceiling fans for our
5 "fan ready" rooms. Steve is taking me there tomorrow to buy my
fluorescents and the other lights, giving me the advantage of his contractor's
discount. Since I did my own wiring, I am getting the difference
in costs, but have to buy my own supplies.
Monday, March 10
When I arrived, the painters were swarming over the outside of the house
calking all the seams and nail heads. Shortly the carpet layers arrived.
Our carpet is going in today. Then Ralph and Ron arrived to do the
drywall touch up. I had removed several switch and outlet plates
where there was work needed. The side shop door needed a LOT of work.
If you remember, it was reversed to open outward just as the painters were
due for the interior paint. Small scraps of drywall had been nailed
around the edge so the door molding could be installed. I pulled
off the molding to give them a chance to really fix the drywall under it.
I headed home to get Betty. We are rock hunting this morning.
We went to the landscaping rock yard where Steve usually gets his supplies
and looked at the various colors of rock. We selected a golden brown
stone called "Cinnamon Brown"). This will be our basic ground cover
around the house.
I headed back to the house (third time today) after taking Betty home.
On the way, I stopped at the cable company and ordered cable TV service.
They install it Wednesday between 3 and 5. Steve had said this afternoon
would be good to go to Home Depot. I could not find him, so called
him on his cell phone. He had unexpectedly needed to go to the lot
where he is building his own home to meet an inspector. He offered
to take me around 5 today, or first thing tomorrow. We decided on
tomorrow.
Meanwhile, Betty had called the phone company and ordered our phone
moved from the motorhome to the house. They will do that on Friday,
March 21, our anticipated move-in date.
Tuesday, March 11
I then went to Home Depot with Steve and bought over $1000 of lights
and supplies! It was very nice of him to make a special trip with
me just so I could get his contractor's discount!
I went home and got Betty. Steve's crew has the car driveway formed,
and the upper part pretty well filled with AB. With a
couple of boards to help bridge the gap between the dirt and the concrete
garage floor, I backed the truck into the garage. Betty now was able
to enter our house for the first time! After taking her around quickly,
I left her to explore while I prepared a couple more fluorescents.
The carpeting looks really good, but there are several areas that show
a line. I assumed these lines were the edge of the vinyl flooring
that was in areas under the carpet. They removed some of it, but
left large areas. When the factory puts down vinyl, they do the full
width of the home-half wherever it is needed in part of the width.
Therefore alongside the kitchen, utility room, and the bathrooms, the vinyl
extends into the living room, the hall, and the master bedroom.
Betty tried walking along and across the seam in the living room, and
was very disturbed by the uneven feel. I could feel it, but it did
not cause the same level of problem it did for Betty. We decided
this problem had to be corrected, and since I had asked them to remove
the vinyl from the carpet areas, and they only did some, they needed to
correct it. Steve called Tai, the carpet layer's boss, and he said
he would check it out.
Wednesday, March 12
I talked to Steve about the situation. He went out and bought
a belt sander and a pack of belts for me to use. I sanded the entire
seam of the living room and applied a little filler. I also "feathered
in" the horseshoe shaped vinyl edge. With the sander it was easy!
I started puttering around with the electrical stuff. I
opened a fluorescent to see what I had to work with. I had placed
all the electrical outlets the lights will plug into near the end of each
fixture, figuring the power cord would exit at the end. The ballast
was installed off center with the power leads pointing toward center!
It would take most of my cord's length just to reach these leads!
The wires to the light sockets were quite long. I discovered I could
remove one screw, turn the ballast around, and the power leads would almost
reach the end of the fixture, and the socket wires were still long enough
to reach the far end of the ballast. Then I discovered the mounting
holes were not symmetrical. The holes I was going to use were in
10 inches on one end and 15 inches on the other. I installed
eyebolts into the 10" hole and a new one I drilled in the other end.
I will chain hang the lights from these eyebolts.
By the time I had my "prototype" light all modified, wired, and bolted,
I had spent almost an hour. I found this time dropped to about half
an hour on the later lights, once I knew what to do.
A little before 3:00, the Cable-One installer came. He was thrilled
with my setup. He was leaving for Cancun in several hours and was
happy to have easy installs. I had expected he would need a ground
wire, so was prepared to crawl under the house. He fed his wire down
though my conduit. I crawled under, pulled the wire about 6 feet
and fed it out through a hole in the siding about a foot from the ground
rod. He was funny - and great! He said in addition to the two
lines I had selected for him to connect I had one additional one coming.
The office girl had said two. He then said being that close to the
distribution box across the street the signal would be very strong.
Why don't I select another couple of lines and he would use a 4 way splitter.
About 5 minutes later he said to pick a couple more and he would use a
6 way one. I thought that was it, but when I checked the finished
installation, I had an 8 way splitter with all my lines connected!
I hope he has a great time in Cancun!
Thursday, March 13
I finished sanding the last layer of filler I let cure overnight and
returned the sander to Steve. I then hung the four "lantern lights"
on the front of the garage and RV garage. After this, I had time
to assemble one more fluorescent, then headed back to the motorhome..
Friday, March 14
About this time Danny and Derirck, the garage door people showed up
with the doors for both garages, and unloaded all the panels, tracks, a
huge commercial opener, and a lot of hardware. It was then he threw
me a blockbuster! He said he just discovered the commercial unit
needed 4 conductor cables for both the controls and the IR safety photocells.
He had previously told me 2 conductor which is what I installed.
My priorities now changed! I spent over an hour crawling in the
garage attic and then the motorhome attic pulling some 8 conductor cat-5
cable in place of the 2 for the main door control. This was quite
a difficult task as the areas were very low clearance at the edges of the
pitched roofs, but had the advantage that I could pull fairly short sections
at a time. It worked! I was able to pull the new cable right
through the same staples in the walls that previously held the 2 conductor
wire.
I tried the same technique to pull 2 new wires along the edge of the
RV garage door. It was a total failure! I was able to pull
the cable about 12 feet of the 12 1/2 feet needed. There was a staple
just a few inches below the top plate that I just could not pull the wire
through! The first wire I tried finally pulled apart where I joined
them. I thought that maybe I could get through that staple with the
second wire now that there was only one wire in it. No luck!
We will go to backup plan #1. I will drill a couple of holes through
the ceiling tight against the corner of the door framing. I can then
run wires along the surface where they will not show TOO much. What
a disappointment after thinking I had all these wires pre-installed!
By the end of the day, the RV garage door was fully installed, but not
the operator. They will be back tomorrow to install the operator
and do the car garage door and operator. I also have a finished driveway,
caps installed on the west wall, re-installed carpet, and all 4 fluorescents
hung in my shop.
Saturday, March 15
After helping Nigel a bit holding heavy parts up while he bolted them
in place, I went to Costco and bought 2 motion sensor floodlights with
fully shielded bulbs (and including bulbs). The mounting system is
much more flexible and user friendly! I bypassed the motion sensor
and installed the one on the back wall of my shop. I procrastinated
installing the one on the side of the RV garage, as the wind has gotten
fierce as the start of a storm system that is due tonight. I really
don't want to work at the top of a ladder (or even outside) in those conditions.
The electrical work is now complete except for this one fixture!
I still have a number of fluorescent lights to install, but they just plug
in to finished sockets. They don't count!
When I left, Nigel had finished the garage door installation and had
just gotten the upper and lower limits set. As happened last Saturday,
Betty called me and asked what my plans were. Church is in less than
an hour!
After church Betty and I drove back to the house. It was all locked
up! Even though there is no opener on the RV door yet, there is a
slide bolt. The garage door is locked by the operator on it.
I entered by the front door, through to the garage and found the owner's
manual with two remote control units on it. They had been programmed
and both work the garage door. They are 3 button units and will work
both units when finished. I took the manual and the remotes and we
left. Now no one but we can enter our house. I will talk to
Steve Monday morning to see what they need from here on.
The movers have instructions to deliver our things NEXT Friday, or as
soon after as their schedule allows. This is very scary! Steve
keeps assuring me we will have a Certificate of Occupancy before then,
but I still worry. I will ask for his assurance again Monday while
there is still time to re-schedule.
Till next time,
Dick
I have posted photos on-line at:
http://members.isp01.net/rmason/statusreports.html
|
|
||||||||||||||||||||||||||||
|
|